重新處理過的光石紅銹鐵板再次運到現場 The rusted iron plates after several times of sandblasting, finally transfer back to the site. |
說明箱移至現場 Moving the caption box back to the site |
說明箱在存放期間,被不知名的人士滴到強力膠 Damage of our caption plate by unknown person with superglue. |
因為基地移設關係,所有光纖都必須剪斷、重新安裝,以確保光纖長度符合移設地點 Cutting off and re-installing the optic fiber to ensure the length is suitable for this new location. |
新運來的光纖=更多支出的經費 New optic fiber = more cost of $$$ |
更換新的燈罩 Replacement of the new terminal fixtures. |
光石上所有的燈罩都全數更新 Renewing the overall terminal fixtures on 光石 |
嚴重侵蝕 Serious erosion |
光纖重新配線完畢 Rewiring the optic fiber |
開始拉線 Wiring work on site |
第二塊光石板 Second rusted iron plate |
因為基地移設關係,所有光纖都必須剪斷、重新安裝,以確保光纖長度符合移設地點 Cutting off and re-installing the optic fiber to ensure the length is suitable for this new location. |
燈罩毀損 Damage of terminal fixtures |
更換新的燈罩 Replacement of the new terminal fixtures. |
光纖重新配線完畢 Rewiring the optic fiber |
安裝插座 Pipeline work finished and installing socket |
作品定位(大) Fixed position (Large plate) |
作品定位(小) Fixed position (small plate) |
安裝光纖管線中 Installing optic fiber lines |
安裝動力系統 Power Installation |
固定基座 Welding foundation |
光纖配線完成 Lining up |
光點製作 Lighting point |
安裝光源機 Installation of Lighting control box |
燈光測試1 Light test 1 |
燈光測試2 Light test 2 |
安裝完畢 終わりました~ |